Effective implementation management and timely contract administration |
A: 119. OSC: Routine/daily administration of work elements |
|
01/31/2026 |
|
Complete all required EC and obtain permits prior to implementation of project work |
B: 165. Produce Environmental Compliance Documentation |
|
01/31/2026 |
|
Completed Progress (Annual) Report |
D: 132. Submit 84063 Rel 10 Progress Report for the period February 2024 to January 2025 |
|
09/30/2025 |
|
Effective implementation management and timely contract administration |
E: 119. IDFG: Upper Salmon Basin Manage and Administer Project |
|
01/31/2026 |
|
Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish |
F: 114. IDFG: Upper Salmon Basin Project Development |
|
01/31/2026 |
|
Cloud-based depository for Upper Salmon Basin |
G: 161. IDFG: Maintain cloud-based repository for habitat project imagery and geo referenced maps for project planning and cooperator use. |
|
01/31/2026 |
|
Construction Management Complete |
H: 100. IDFG-Lemhi-Construction Oversight and Management |
|
01/31/2026 |
|
Complete Adaptive Management Phase 2 of the Lower Lemhi Rehabilitation Project |
I: 29. IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 1 Adaptive Management Phase 2 |
|
01/31/2026 |
|
Lower Lemhi Rehabilitation Project Phase 2 Revegetated |
J: 47. IDFG-Lemhi- Revegetation of Eagle Valley Ranch sub reach 1 phase 2. |
|
01/31/2026 |
|
Lower Lemhi Rehabilitation Project Phase 3 Complete |
K: 29. IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 1 Phase 3 Implementation |
|
11/01/2025 |
|
Complete initial planting on Phase 3. |
L: 47. IDFG-Lemhi- Revegetation of Eagle Valley Ranch sub reach 1 phase 3. |
|
12/31/2025 |
|
Pivot Installed |
M: 208. IDFG-Lemhi-Pivot for EVR subreach 1 phase 3. |
|
09/30/2025 |
|
Construct Phase 4 of the Lower Lemhi Rehabilitation Project |
N: 29. IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 1 Phase 4 Implementation |
|
01/31/2026 |
|
Initial planting for phase 4 |
O: 47. IDFG-Lemhi- Revegetation of Eagle Valley Ranch sub reach 1 phase 4. |
|
01/31/2026 |
|
Subreach 4 construction complete |
P: 29. IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 4 |
|
01/31/2026 |
|
Maintain Vegetation |
Q: 198. IDFG-Lemhi-Maintain Vegetation EVR Subreach 1 Phases 1, 2, 3, and 4. |
|
01/31/2026 |
|
Middle Lemhi Hayden Creek Phase 2 design complete |
R: 175. IDFG-Lemhi- Middle Lemhi Henry Reach Phase 2 Design |
|
10/31/2025 |
|
Henry Phase 2 project complete |
S: 29. IDFG-Lemhi- Middle Lemhi Henry Reach Phase 2. |
|
01/31/2026 |
|
Fence construction |
T: 40. IDFG-Lemhi- Middle Lemhi Henry Reach Phase 2 Fencing |
|
01/31/2026 |
|
Middle Lemhi Henry Project revegetated |
U: 47. IDFG-Lemhi- Middle Lemhi Henry Reach Phase 2 Revegetation |
|
01/31/2026 |
|
Complete Hayden Reach Phase 2 Design |
V: 175. IDFG-Lemhi- Middle Lemhi River-Hayden Reach Phase 2 Design |
|
01/31/2026 |
|
Complete construction of Hayden Phase 2 project. |
W: 29. IDFG-Lemhi- Middle Lemhi River-Hayden Reach Phase 2 Implementation |
|
01/31/2026 |
|
Construct and Install or Replace Well |
X: 208. IDFG- Lemhi- McNeal Wells |
|
01/31/2026 |
|
Final Design for Beyeler Irrigation System |
Y: 175. IDFG - Lemhi: Beyeler Ranch Irrigation System Design |
|
01/31/2026 |
|
Pipeline purchased |
Z: 208. IDFG - Lemhi: Beyeler Ranch Irrigation System Purchase of Pipeline |
|
01/31/2026 |
|
Perform unscheduled maintenance on habitat/passage/structure as needed. |
AA: 186. IDFG: Perform Unscheduled Maintenance of Habitat Project Sites in the Upper Salmon Basin |
|
01/31/2026 |
|
Construction Management Complete |
AB: 100. IDFG-Pahsimeroi-Construction Oversight and Management |
|
01/31/2026 |
|
Last Chance Ranch Phase 2 complete |
AC: 29. IDFG-Pahsimeroi-Last Chance Ranch Upper Pahsimeroi Phase 2 |
|
01/31/2026 |
|
Fence habitat on Last Chance Ranch Phase 2 |
AD: 40. IDFG-Pahsimeroi-Last Chance Ranch-Upper Pahsimeroi Phase 2 Fencing |
|
01/31/2026 |
|
Revegetate habitat restoration project |
AE: 47. IDFG-Pahsimeroi-Last Chance Ranch-Upper Pahsimeroi Phase 2 Revegetation |
|
01/31/2026 |
|
Vegetation maintained on completed restoration projects. |
AF: 198. IDFG - Upper Salmon River Implementation Project Vegetation Maintenance |
|
12/01/2025 |
|
Final Design for bridges complete |
AG: 175. IDFG-Upper Salmon-Bia Po’i Naokwaide (SQ) Creek culvert to bridge design |
|
10/31/2025 |
|
Complete passage project |
AH: 184. IDFG-Upper Salmon-Bia Po’i Naokwaide (SQ) Creek double culvert to bridge project |
|
12/31/2025 |
|
Final design for Poison Creek culvert to bridge project complete |
AI: 175. IDFG-Upper Salmon-Poison Creek Culvert to Bridge Design |
|
01/31/2026 |
|
Final construction ready designs for Kinnikinic Creek |
AJ: 175. IDFG-Upper Salmon-Kinnikinic Creek Culvert to Bridge Design |
|
01/31/2026 |
|
Final Design for EF Tower Road Culvert to Bridge |
AK: 175. IDFG-Tower Creek- East Fork Tower Creek Road-Culvert Removal Design |
|
01/31/2026 |
|
Final construction ready designs for implementation |
AL: 175. IDFG-Pahsimeroi-Hanging T Ranch Ranch Plan Design |
|
01/31/2026 |
|
Complete well testing, well construction approval and final design for irrigation system. |
AM: 175. Custer SWCD - Develop well design and complete well test to develop well for P12 source switch. |
|
12/26/2025 |
|
Complete well development and installation of Irrigation Pump in New Well |
AN: 203. Custer SWCD - Install well to replace P12/13 surface water in order to allow more water in-stream in the middle reach of the Pahsimeroi. |
|
09/05/2025 |
|
Complete final design and seek funding for project implementation |
AO: 175. Custer SWCD - Develop design for Kinnikinic County Culvert |
|
01/31/2026 |
|
Effective implementation management and timely contract administration |
AP: 119. Lemhi SWCD: Project Implementation: Manage and Administer |
|
01/31/2026 |
|
Construction Management Complete |
AQ: 100. Lemhi SWCD Project Implementation: Provide Project Implementation Support & Construction Oversight |
|
01/31/2026 |
|
Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish |
AR: 114. Lemhi SWCD Project Implementation: Identify and Select Projects |
|
01/31/2026 |
|
Invasive and Noxious Weed Species Treated and all subsequent reporting submitted |
AS: 199. Lemhi SWCD: Lemhi Vegetation: Initial treatment |
|
01/31/2026 |
|
Treat noxious weeds at identified sites and submit HUF and PCFs |
AT: 199. Lemhi SWCD: Pahsimeroi Vegetation: Initial treatment |
|
01/31/2026 |
|
Treat sites for noxious weeds and submit all HUFs and PNF |
AU: 198. Lemhi SWCD: Lemhi Vegetation: Ongoing treatment |
|
01/31/2026 |
|
Treat sites identified for noxious weeds and submit HUFs and PCF |
AV: 198. Lemhi SWCD: Pahsimeroi Vegetation: Ongoing treatment |
|
01/31/2026 |
|
Complete all planting and seeding and submit PCF |
AW: 47. Lemhi SWCD: Lemhi Vegetation Management: Rehabilitate Project Sites, Initial Treatment |
|
01/31/2026 |
|
Complete planting and seeding and submit PCF |
AX: 47. Lemhi SWCD: Pahsimeroi Vegetation Management: Rehabilitate Project Sites, Initial Treatment. |
|
01/31/2026 |
|
Project implementation completed |
AY: 29. Lemhi SWCD: Lemhi River at Kenney Creek Implementation |
|
01/31/2026 |
|
Final Designs completed |
AZ: 175. Lemhi SWCD: L-45 Restoration and Diversion Design |
|
01/31/2026 |
|
Effective implementation management and timely contract administration |
BA: 119. MHE: USB Manage and Administer |
|
01/31/2026 |
|
Attend Upper Salmon Basin Tech Team, Subcommittee or Advisory Committee meetings |
BB: 191. MHE: Watershed Coordination of the Upper Salmon Basin |
|
01/31/2026 |
|
Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish |
BC: 114. MHE: Identify and Select Projects in the Upper Salmon Basin |
|
01/31/2026 |
|
Adaptive management complete |
BD: 186. TU: Beyeler Upper Mainstem/Springs Adaptive Management |
|
01/31/2026 |
|
Produce Environmental Compliance Documentation |
BE: 165. TU: Elk Meadows Trail Relocation and Habitat Restoration Project NEPA |
|
01/31/2026 |
|
Lemhi Reference Reach Phase 2 Construction Complete |
BF: 29. TU: Lemhi Reference Reach Phase 2 |
|
01/31/2026 |
|
Seeding Completed |
BG: 47. TU: Lemhi Reference Reach Phase 2 |
|
01/31/2026 |
|
Produce Design for Bar G Muddy Springs Design |
BH: 175. TU: Bar G Muddy Springs Design 2025 |
|
01/31/2026 |
|
Complete installation of Bar G Muddy Springs Irrigation Infrastructure |
BI: 208. TU: Bar-G Muddy Spring Habitat Phase 1 - Irrigation infrastructure construction |
|
01/31/2026 |
|
New side channel construction, in stream habitat construction, floodplain grading completed. This work will be conducted outside of live water. |
BJ: 29. TU: Lemhi RM32 Habitat Enhancement Project - Island Phase |
|
01/31/2026 |
|
Seeding Completed |
BK: 47. TU: Lemhi RM32 Habitat Enhancement Project - Island Phase |
|
01/31/2026 |
|